Tuesday, November 13, 2012

Infrastructure Renewal Team SAK/Quest Completes Austin's Downtown Wastewater Tunnel

Infrastructure Renewal Team SAK/Quest Completes
Austin’s State-of-the-Art $40 Million Downtown Wastewater Tunnel

SAK digs deep to create long-lasting infrastructure for Austin’s booming population 

ST. LOUIS (November 12, 2012) ‒ Far beneath the surface of Austin’s popular Lady Bird Lake‒a handsome 416-acre water reservoir that provides recreational opportunities as well as flood control‒years of  intense “dirty work” took place, largely unnoticed by local citizens, as crews labored to create a huge wastewater tunnel that ran as deep as 80 feet underground. As might be expected, the technological and safety challenges of excavating a 4-mile-long, downward-sloping tunnel along a path that runs parallel to a river and underneath a lake at three different locations were considerable. But the need for a true state-of-the-art, gravity-powered wastewater system to accommodate Austin’s growing population well into the future was apparent to City of Austin planners. To tackle the job, the city brought in the joint venture team of SAK/Quest, consisting of St. Louis area-based SAK Construction and Quest Civil Constructors Inc. of Phoenix, along with Parsons Engineering. The tunnel, which was recently completed, is expected to last with minimal maintenance for at least a century—twice as long as the antiquated system it replaced.
Construction on the $40 million tunnel began in early 2010. The project required deep, large-diameter tunnel excavation, a sophisticated type of tunneling that calls for highly specialized expertise and equipment, which SAK, a nationally known provider of pipeline rehabilitation, CIPP and tunneling, offers. The project included approximately 20,554 linear feet of tunnel and utilized 121-inch and 84-inch diameter tunnel boring machines. In addition, SAK/Quest lined the tunnel with pipeline using the latest high-tech materials designed for long life and low maintenance. The Downtown Wastewater Tunnel is managed by the City of Austin Public Works Department.
Challenges to project team
How to perform deep excavation on the tunnel‒which closely parallels the Colorado River for much of its length as well as crossing underneath the lake‒was, of course, the major challenge for the SAK/Quest team. To allow tunnel construction access from five surface locations for the initial segment of the tunnel, SAK/Quest crews constructed four shafts to depths of 75-to-80 feet.   In addition, the team set up bypass sewerage pumping to allow an existing lift station to be cleaned and converted into a fifth shaft.
Working safely so deep underground is partly dependent on the composition of the ground layers above.  During the excavation process, the SAK/Quest crew encountered one particularly challenging area of low rock cover.  “In an area with less than three feet of weathered and broken rock separating the tunnel from 50 feet of sand and an unlimited supply of groundwater above the rock, the risk of catastrophic failure that could endanger the tunnel workers, city property, a nearby railroad and the general public, was a major concern,” says James Byrd, senior project manager for SAK. “The project team went to work to find an answer. SAK/Quest offered a solution to lower the tunnel, yet still maintain a downward slope to keep the sewer flowing by gravity. The city ordered additional geotechnical drilling and Parsons engineered a risk-reducing design incorporating the SAK/Quest solution. Subsequently, the risk was greatly reduced, and the new design resulted in the tunnel being safely and successfully excavated through this area.”
Benefits to the city and its residents
The Downtown Wastewater Tunnel and the pipeline installed inside it dramatically expand the system’s capacity to a level that is expected to accommodate the area’s projected population growth for the next 60 years. The tunnel replaces an inadequate system of 50-year-old, deteriorated concrete pipeline and the associated lift stations that were previously necessary to power wastewater through the sewer system. By installing a sloping tunnel that instead utilizes gravity, the city was able to eliminate the need for two lift stations that many residents considered a blemish on the downtown scene. 
In addition, the tunnel houses glass-fiber-reinforced polymer mortar pipe that is expected to last at least 100 years. “SAK/Quest installed centrifugally cast fiberglass reinforced pipe, which, unlike concrete, is not susceptible to the corrosive effects of sewer gas,” says Byrd.  “Special cement-free polymer mortar manholes‒the largest in diameter of their kind in the nation‒were also constructed at the city’s request.  Through the use of these new corrosion-resistant materials, SAK/Quest dramatically reduced potential maintenance and repair costs, resulting in a potential savings of tens of millions of dollars over the lifetime of the wastewater system.”
SAK Construction, led by industry veterans Jerry Shaw, president; Robert Affholder, vice chairman; and Tom Kalishman, chairman and CEO, is one of the fastest growing, privately held pipeline rehabilitation, CIPP and tunneling contractors in the U.S., with 300 employees working on projects in 28 states.  In the most recent annual ENR (Engineering News Record) survey of national specialty contractors, SAK Construction was named to two separate lists, ranking 7 on “The Top 20 Firms in Utility” and 214 on “The Top 600 Specialty Contractors.”
SAK provides specialized, high-demand infrastructure renewal services ranging from large diameter tunneling to the full spectrum of current trenchless or “no dig” technologies, including CIPP (cured-in-place pipe) pipeline rehabilitation for sanitary and storm sewers and Aqua-Pipe® for drinking water mains from 6 inches to 16 inches in diameter. SAK is an exclusive licensee for Aqua-Pipe in an 11-state region and a contract partner of three cooperative purchasing organizations based in Texas.  The organizations, which serve government entities nationwide, include Choice Facility Partners and The Cooperative Purchasing Network, both in Houston, and BuyBoard in Austin.  SAK clients include a variety of city, county and state agencies; industrial sectors; the federal government and municipalities; and water and sewer cooperatives coast-to-coast.
# # #
(News media--For photos or additional information, contact Patricia Binder, 636.441.0022, or Debra Finkel, 314.878.2465, Finkel & Associates PR & Marketing Communication LLC, agent for SAK Construction.)

Tuesday, June 5, 2012

SAK Completes Challenging MSD Lemay Tunnel






News from:         SAK Construction
                          864 Hoff Road
                          O’Fallon, MO 63366
                          www.sakcon.com

CIPP AND TUNNELING CONTRACTOR SAK CONSTRUCTION COMPLETES CHALLENGING
$10.875 MILLION MSD LEMAY TUNNEL

SAK Digs In to Complete Stalled Excavation Work 
For Lemay Wastewater Treatment Plant
Wet Weather Expansion Outfall Sewer Project

ST. LOUIS (June  5, 2012) – When unexpected ground conditions put a sudden halt to initial efforts to excavate a new 558-foot-long, 16-foot-diameter tunnel leading from the Lemay Wastewater Treatment Plant, the Metropolitan St. Louis Sewer District reissued the project for bid to find a contractor equipped for the challenge.  The project award, which included pipe installation as well as tunneling, then went to SAK Construction, a national pipeline rehabilitation, CIPP and tunneling services contractor headquartered in O’Fallon, Mo.  SAK began work in December 2010 and completed the $10.875 million project, formally named the Lemay Wastewater Treatment Plant Wet Weather Expansion Outfall Sewer project, in approximately 16 months.  The completed outfall sewer line is now in service, providing a new effluent discharge line from the Lemay Wastewater Treatment Plant to a structure on the west bank of the Mississippi.

The scope of work on this project included an extensive tunnel excavation of 381 linear feet. A tunnel boring machine excavated the tunnel to just over 11 feet; crews then went in using non-explosive and explosive rock methods to further widen the tunnel to a 16-foot-diameter horseshoe shape to accommodate the installation of concrete pipe segments that were 12 feet long and 132 inches in diameter.  In addition to difficult ground conditions, challenges encountered and resolved by the SAK team included the discovery of a previously unknown and unmarked sanitary tunnel, which caused flooding during tunnel excavation and required the erection of a temporary bypass pumping operation.

The project was designed by Black & Veatch. The construction management team representing MSD on this project was KAI Design & Build.

SAK is one of the fastest growing, privately held pipeline rehabilitation, CIPP and tunneling contractors in the U.S., with 300 employees working on projects in 28 states.  SAK provides specialized, high-demand services ranging from large diameter tunneling to the full spectrum of current trenchless or “no dig” technologies, including CIPP (cured-in-place pipe) pipeline rehabilitation for sanitary and storm sewers and Aqua-Pipe® for drinking water mains from 6 inches to 16 inches in diameter. SAK is an exclusive licensee for Aqua-Pipe in an 11-state region and a contract partner of three cooperative purchasing organizations based in Texas.  The organizations, which serve government entities nationwide, include Choice Facility Partners and The Cooperative Purchasing Network, both in Houston, and BuyBoard in Austin.  SAK clients include a variety of city, county and state agencies; industrial sectors; the federal government and municipalities; and water and sewer cooperatives coast-to-coast.

In the most recent annual ENR (Engineering News Record) survey of national specialty contractors, SAK Construction was named to two separate lists, ranking 7 on “The Top 20 Firms in Utility” and 214 on “The Top 600 Specialty Contractors.”
# # #
(News media--For photos or additional information, contact Patricia Binder, 636.441.0022, or Debra Finkel, 314.878.2465, Finkel & Binder Communications, LLC, agent for SAK Construction.)

Tuesday, January 31, 2012

CIPP AND TUNNELING EXPERT SAK CONSTRUCTION ADDS TWO TO BUSINESS TEAM Pipeline rehabilitation and tunneling services contractor adds Addington and Shaw in St. Louis


ST. LOUIS (January 31, 2012) – SAK Construction, a national pipeline rehabilitation and tunneling services contractor headquartered in the St. Louis area, has added Gerald Addington and Cary Shaw to its management and business development and marketing team. SAK provides specialized, high-demand services ranging from large diameter tunneling to the full spectrum of current trenchless or “no dig” technologies, including CIPP (cured-in-place pipe) pipeline rehabilitation.

Addington has been named general manager of SAK’s Central Rehabilitation Division. Addington has previously held several senior management positions in the water, underground pipeline and power industries, and brings to SAK more than 30 years of industry experience.  He has managed business units, some of which exceeded $100 million in annual revenue, across the U.S. Addington has completed graduate courses toward a master of science degree in engineering administration and holds a bachelor of science degree from the University of Tennessee in Knoxville.

Shaw joins SAK’s business development and marketing team as business development leader for the firm’s spiral wound PVC pipe renewal division.  Shaw served more than 17 years in the construction industry as business development leader in the commercial/residential area and has developed several commercial and residential land tracts. He holds a bachelor of arts degree in business administration from Benedictine College in Atchison, Kan. Shaw is a member of the Association of General Contractors of America.  

SAK Construction is one of the fastest growing, privately held pipeline rehabilitation and tunneling contractors in the U.S. and currently has projects in 26 states. SAK provides the newest underground trenchless technologies for pipeline rehabilitation using its CIPP (cured-in-place pipe) system for sanitary and storm sewers, and Aqua-Pipe® for drinking water mains from 6 inches to 16 inches in diameter. SAK is an exclusive licensee for Aqua-Pipe in an 11-state region and a contract partner of Choice Facility Partners, a Houston-based nonprofit cooperative purchasing organization serving government entities nationwide. SAK clients include a variety of city, county and state agencies; industrial sectors; the federal government and municipalities; and water and sewer cooperatives coast-to-coast.

In the most recent annual ENR (Engineering News Record) survey of national specialty contractors, SAK Construction was named to two separate lists, ranking 7 on “The Top 20 Firms in Utility” and 214 on “The Top 600 Specialty Contractors.”
# # #
(News media--For photos or additional information, contact Patricia Binder, 636.441.0022, or Debra Finkel, 314.878.2465, Finkel & Binder Communications, LLC, agent for SAK Construction.)